Development Careers Subcontractors Login (616) 363-3825

Napa Parking Lot Addition

Visser Brothers » Projects » Napa Parking Lot Addition

Napa Parking Lot Addition

Location:  3402 Patterson Ave. SE, Grand Rapids, MI 49512

Type of Work:  Parking lot addition

Total floor parking space:  67,000 SF

Value:  $650k

Date Completed:  8/23/2024

Visser Brothers excavated 150,000 square feet of undeveloped land, carefully working in close proximity to wetlands to expand an existing employee parking lot and provide additional spaces for semi-truck overflow.  A detention pond was constructed to manage storm water runoff.  The existing truck turnaround area was demolished and replaced with newly poured concrete.  This project was completed in 2 months from start to finish, from June to August 2024.